Roundhouse Renovation Project – Progress Update
February 18, 2026
Overall Project Progress
Work continues throughout the building, with multiple work streams underway at the same time. Most installations are progressing smoothly. A limited number of units remain on hold due to access or preparation requirements.
Bathroom Fan Installation
- Bathroom fans installed to date: 134 units
- Most installations are completed within one day, with a temporary ceiling cover installed
- Archway has begun scheduling finishing work in the bathrooms (boarding, mudding, and painting)
Boarding, Mudding and Painting in the Units
At the same time that bathroom work is being completed, Archway will also finish any remaining boarding, mudding, and painting in other areas of the unit where this work was previously left incomplete.
Reprogramming and Commissioning of the Fan Coil Units
Archway is actively carrying out the reprogramming and commissioning of fan coil units in members’ units where the related installation work has been completed. This process typically takes up to 30 minutes per unit and is expected to resolve the majority of reported issues.
Shaft Work (Between Stacks 012 & 013)
- Vent removal, plumbing, insulation, electrical, and mechanical wiring complete
- Shaft closure in progress, floor by floor
- New vent installation to follow
Mechanical Room
- Upgrade work is ongoing
- New hot water tanks have been installed and are under monitoring EV Charger Conduit and Junction Boxes Installation (Parking Area)
- Majority of work completed (total 36 stalls)
- Limited additional work may be required in some individual parking stall Further updates will be provided as the project progresses.
Important Reminders
Access to the unit
When proper notice of entry has been provided:
- Contractors are authorized to enter even if the member is not present
- Entry may not be denied for required work under the Occupancy Agreement
- If a member has a valid reason (e.g., illness), they should contact Members’ Liaison or Archway’s Foreman as early as possible to request rescheduling
Deficiencies The fastest and most efficient way to address any deficiencies or issues is to report them directly to the Members’ Liaison or Archway’s foreman. Prompt reporting helps ensure timely review and resolution.